GigaclearGigaclear have made good progress laying the new fibre optic cables and have reached the pub from the top of The Street. The Borough Council has now suggested that they stop works as continuing the works requires a road closure.

Work will resume on 18th May and the plan is to get down to Long Mill Lane in 3 weeks. This will overlap with half term for one of the weeks. Work is unable to progress during the Easter holidays due to a UK Power Network road closure (see separate news item).

Gigaclear have not left the area; they are working along Hildenborough Road heading into Shipbourne.